

Turbine

Generator

Solar Turbines - GTG



Turbine

Generator

Solar Turbines - GTG









Module 6 upper deck installation

Module 1 from Module 2

Compressor's location

Compressors (cannot open-client's requirement)

Padlock task (LOTO System)




Housekeeping in progress

DANGER !!

Supervisors are giving orders to sub-con

One of a room in LQ
View from Office




Normal VS Emergency Light



Starters panel
After lunch, I studied all the plan related to Module 6 and asked question about the switchgear room in Module 6. Performed lighting cable schedule for all modules and identify each cables and separate it according to it's usage. Also generate formulas to calculate the percentage of completion.
On the way to site for toolbox meeting
One of the Junction Box (JB) at MSF
View of Module 7 (Living Quarters)
Switchgear Room in Module 6
Air Circuit Breaker used in Switchgear RoomI studied back the diagram of MSF and also the cable schedule of MSF and its relation. Besides that, I also did some documentation and updating cable schedule from the report of technicians.

After that, I studied each module's documentation including the flow diagram, single line diagram, power, control, heater, lighting, small power cable and types of circuit breakers. Also, did some preparations before entering site tomorrow.


Examples of LOTO System

Miniature Circuit Breaker (MCB)
Moulded Case Circuit Breaker (MCCB)
Vacuum Circuit Breaker (VCB)
Air Circuit Breaker (ACB)
Performing cable schedule analysis
I obtained result from yesterday safety introduction talk, passed with 45/50.
Continued working on cable schedule analysis. I also did the preparation on padlocks, labelling to it on each locks and keys. This is to lock all the circuit breakers and to avoid it from energized by unauthorized people. Overtime till 10.00pm.


